Cohesion Policy Incentives for Businesses (2000-2024)
Open Cohesion Project
UDR HIEHYPWT (PODIUM ENGINEERING SRL- POLITECNICO TO-HONESTAMP SRL-VALL?E TRAFOR SRL-ELTEK SPA)
Project Code
4VAICO0110416AL00007RIQ
Cycle
Ciclo di programmazione 2014-2020
Sector
Sector Not Available
Municipality
Allein
Province
Valle d'Aosta/Vallée d'Aoste
Region
Valle d'Aosta/Vallée d'Aoste
Macro Area
Nord-ovest
Multi-located project
Allein (AO), Antey-Saint-Andr? (AO), Aosta (AO), Arnad (AO), Arvier (AO), Avise (AO), Ayas (AO), Aymavilles (AO), Bard (AO), Bionaz (AO), Brissogne (AO), Brusson (AO), Ch?tillon (AO), Challand-Saint-Anselme (AO), Challand-Saint-Victor (AO), Chambave (AO), Chamois (AO), Champdepraz (AO), Champorcher (AO), Charvensod (AO), Cogne (AO), Courmayeur (AO), Donnas (AO), Doues (AO), Emar?se (AO), Etroubles (AO), F?nis (AO), Fontainemore (AO), Gaby (AO), Gignod (AO), Gressan (AO), Gressoney-La-Trinit? (AO), Gressoney-Saint-Jean (AO), H?ne (AO), Introd (AO), Issime (AO), Issogne (AO), Joven?an (AO), La Magdeleine (AO), La Salle (AO), La Thuile (AO), Lillianes (AO), Montjovet (AO), Morgex (AO), Nus (AO), Ollomont (AO), Oyace (AO), Perloz (AO), Pollein (AO), Pont-Saint-Martin (AO), Pontboset (AO), Pontey (AO), Pr?-Saint-Didier (AO), Quart (AO), Rh?mes-Notre-Dame (AO), Rh?mes-Saint-Georges (AO), Roisan (AO), Saint-Christophe (AO), Saint-Denis (AO), Saint-Marcel (AO), Saint-Nicolas (AO), Saint-Oyen (AO), Saint-Pierre (AO), Saint-Rh?my-en-Bosses (AO), Saint-Vincent (AO), Sarre (AO), Torgnon (AO), Valgrisenche (AO), Valpelline (AO), Valsavarenche (AO), Valtournenche (AO), Verr?s (AO), Verrayes (AO), Villeneuve (AO)
EU Funding
€ 322.500,00
Total Funding
€ 645.000,00
Cohesion Cost
€ 645.000,00
Commitments
€ 645.000,00
Total payment
€ 632.067,00
Start Year
2016
Expected End Year
2019
End Year
2020
Year of payments
2016
2018
2020
2018
2020
Payments (per year)
€ 21.890,40 (2016)
€ 349.982,00 (2018)
€ 260.194,00 (2020)
€ 349.982,00 (2018)
€ 260.194,00 (2020)
Open Coesione Link